Panel For Example Panel For Example Panel For Example

Power Room Shutdown and Re-energization Sequence

Author : Adrian September 25, 2025

Shutdown and Re-energization Order

The order of shutdown and re-energization must not be confused.

General rule: during shutdown, de-energize low-voltage circuits first, then high-voltage circuits. During re-energization, follow the reverse order.

When de-energizing low voltage, first open the low-voltage branch switches, then the low-voltage main switch. Also stop control circuits before the main circuits. For re-energization, reverse this order.

When de-energizing high voltage, trip the circuit breaker first, then open the isolating switch. For incoming high-voltage lines with two isolating switches, open the load-side isolator first, then the source-side isolator. For re-energization, reverse this order.

It is strictly prohibited to operate isolating switches under load.

Re-energization Operation Procedure

The re-energization steps are as follows:

  1. After confirming that no personnel are working on any electrical equipment in the distribution room, remove temporary grounding wires and warning tags. When removing grounding, detach the line end first, then the grounding end.
  2. Verify that the switches on both incoming lines WL1 and WL2 are in the open position, then close the tie isolator between the two high-voltage buses WB1 and WB2 so WB1 and WB2 can operate in parallel.
  3. Sequentially close all isolating switches on WL1, then close the incoming line circuit breaker. If the breaker closes successfully, WB1 and WB2 are intact.
  4. Close the isolating switches of the voltage transformer circuits connected to WB1 and WB2, and check that the supply voltages are normal.
  5. Close all high-voltage outgoing isolating switches, then close all high-voltage outgoing circuit breakers to energize the main transformers serving the distribution room.
  6. Close the knife switch on the low-voltage side of No.2 distribution room's main transformer, then close the low-voltage circuit breaker. If the breaker closes successfully, the low-voltage bus is intact.
  7. Check the low-voltage readings using the voltmeters connected to both low-voltage buses.
  8. Close all low-voltage outgoing knife switches in No.2 distribution room, then close the low-voltage circuit breakers or fuse-type knife switches to energize all low-voltage outgoing circuits. At this point the high-voltage substation and its connected workshop substations are fully brought into service.

Fault Recovery Considerations

If re-energizing after a fault-induced outage, the procedure depends on the type of switchgear installed on the incoming line.

If the incoming line is equipped with a high-voltage circuit breaker, the breaker will trip automatically for a short-circuit on the high-voltage bus. After the fault is cleared, the breaker can be reclosed directly to restore supply.

If the incoming line uses a high-voltage load switch with fuses, replace the fuse elements after the fault is cleared before closing the load switch to re-energize.

If the incoming line uses an isolator-and-fuse arrangement, after the fault is cleared replace the fuse link, open all outgoing switches, then close the isolator, and finally close all outgoing switches to restore supply. The same procedure applies when the incoming line uses drop-out fuses.

Recommended Reading
Purpose and Requirements of Automatic Reclosers

Purpose and Requirements of Automatic Reclosers

September 25, 2025

Overview of automatic reclosers, advantages, risks, and implementation principles for single-phase adaptive reclosing and comprehensive automatic reclosing in power systems.

Article
Substation Secondary Systems: Common Equipment

Substation Secondary Systems: Common Equipment

September 25, 2025

Technical overview of terminal block design and front panel layout principles for secondary equipment, covering terminal types, arrangement, and panel diagrams.

Article
Responding to High-Power Outages in Outdoor Construction

Responding to High-Power Outages in Outdoor Construction

September 25, 2025

Review of portable power options and large-capacity mobile energy stations for prolonged, high-power outages: specifications, output, cycle life, safety, and deployment.

Article
Are AC Terminals the Same as AC Cables? Inverter Installation Steps

Are AC Terminals the Same as AC Cables? Inverter Installation Steps

September 25, 2025

Technical guide to inverter AC cable selection for residential and commercial installations, comparing copper and aluminum conductors and outlining wiring and commissioning steps.

Article
When to De-energize a Transformer for Inspection

When to De-energize a Transformer for Inspection

September 25, 2025

Classification of transformer defects (urgent, major, general), emergency fault indicators, response time targets, and de-energization criteria for oil and cooling failures.

Article
Breaker Categories and 10/350, 8/20 Surge Parameters

Breaker Categories and 10/350, 8/20 Surge Parameters

September 25, 2025

Technical overview of breakers (CAT A/B), RCBO/RCCB/RCD, surge protector waveforms (10/350, 8/20), IP ratings for switchgear, and transformer hum causes and mitigation.

Article